How much steam a slate plant needs: estimating the boiler

Boiler capacity is worked out not from the floor area of the shop and not from a salesman's advice, but from the steam consumers: how much heat goes into warming the autoclave, the cars and the sheets, how much is lost through the walls and the steam line, and how often the cycles overlap. The main consumer is the heat-up: the peak rests on it. Then the boiler figure is converted from the nominal one to the actual one: it depends on the pressure and on the feedwater temperature.

Updated 10 min read

In short

10minutes to read

8sections

9sources

4catalog items

In this article

  1. 01What the owner and the chief mechanic need to decide
  2. 02Where a slate plant needs steam
  3. 03How to calculate steam consumption for heat-up
  4. 04Example: one autoclave
  5. 05From consumers to the boiler
TableHow to calculate steam consumption for heat-up3 rows →
Contents
  1. What the owner and the chief mechanic need to decide
  2. Where a slate plant needs steam
  3. How to calculate steam consumption for heat-up
  4. Example: one autoclave
  5. From consumers to the boiler
  6. What to send the plant to select a boiler
  7. Safety
  8. How we do it

The steam output of a boiler for a slate plant is worked out from the steam consumers. On an autoclave line the main consumer is the autoclave; on a natural-curing line it is the steam curing chambers. Steam is needed to heat the metal of the autoclave and the cars, the sheets themselves and the water in them, and to cover the heat lost through the walls. Most steam goes at the start of the cycle, during the heat-up. So the boiler is chosen for the peak that really occurs in your shop, not for the sum of the table figures of all the machines. Below is how to make an estimate yourself, on what example to check the order of the figures, and what to ask the manufacturing plant afterwards.

What the owner and the chief mechanic need to decide

  • Which consumer to calculate by. List all the steam consumers: autoclaves, steam curing chambers, heating of water and mass, heating of the shop if it is steam heating. For each you need the regime: to what temperature to heat and in how much time.
  • Peak or average. The heat-up of an autoclave is short and heavy, the hold is long and light. If two autoclaves start heating at the same time, the peak doubles. The schedule of cycles affects the size of the boiler as much as the autoclave itself.
  • Whose figure is in the passport. A boiler in a catalogue is often rated "from and at 100 °C". The real output at your pressure and with your feedwater is lower.
  • How to check a boiler already in operation. On running equipment it is better to measure the consumption with a steam flowmeter than to calculate it.

Where a slate plant needs steam

Steam curing chambers. In the textbook by I. A. Rybyev the curing regime of asbestos-cement products in steam curing chambers is given as follows: 50–60 °C, relative humidity 90–95 %, 10–14 hours, then 5–7 days in an insulated warehouse. The temperature is not high, but the chambers are large, and steam goes into heating the chambers themselves, the sheets and the spacers, and into losses through the enclosures.

Autoclave. The same source says that in the autoclave the products cure under steam at a pressure of 0.8 MPa, and this allows sandy cement to be used. If 0.8 MPa is the gauge pressure by the pressure gauge, the absolute pressure will be about 0.9 MPa, and by the saturated steam tables the saturation temperature at it is about 175 °C. Patent US 7972433 on a fibre cement sheet describes an autoclave regime: a rise to 150–180 °C in 3.5 hours, a hold of 6.5 hours, a decrease over 6 hours. Before the autoclave the sheet cures at 40–80 °C for 12 to 24 hours. This is an example from one patent, not a norm: the regime of your line is in the process regulations and in the autoclave passport.

How to calculate steam consumption for heat-up

The method is taken from the engineering materials of Spirax Sarco. Steam consumption for heat-up depends on the mass and heat capacity of what is being heated, on by how many degrees it is heated, on the latent heat of the steam and on the time allowed for the heat-up.

Heat for heat-up, kJ = mass, kg × heat capacity, kJ/(kg·°C) × temperature rise, °C.

Steam, kg = heat for heat-up, kJ ÷ latent heat, kJ/kg.

Average consumption, kg/h = steam, kg ÷ heat-up time, h.

What to put in:

What is heatedHeat capacityWhere the figure comes from
Steel: autoclave shell, lid, cars, rails inside0.49 kJ/(kg·°C)Spirax Sarco, worked example of heating a steel steam pipe
Dry part of the sheetabout 0.9 kJ/(kg·°C)EN 1992-1-2 for dry concrete: 900 J/(kg·K) at 20–100 °C, above 100 °C the value grows. For fibre cement this is an approximation
Water in the sheetabout 4.19 kJ/(kg·°C)NIST tables of water properties

The latent heat is taken from the saturated steam tables for the pressure at which the steam gives up its heat. By the NIST tables at an absolute pressure of about 0.9 MPa (175 °C) it is about 2030 kJ/kg, at 1.0 MPa about 2015 kJ/kg. The higher the pressure, the lower it is, so more steam is needed for the same heat.

Take the mass of the steel of the autoclave and the cars from the passport or the plant's specification. Take the mass of the sheets in the load and their moisture from your own measurement: weigh the load, dry a sample and work out the share of water.

Example: one autoclave

The figures of the example are conditional. They are needed to see the order of magnitude and the weight of each part. Your masses will be different.

Suppose the shell, lid and cars together weigh 70 t of steel, the load is 60 t of sheets, of which 12 t is water (20 %). We heat from 20 to 175 °C, that is by 155 °C, in 3.5 hours.

PartCalculationHeat
Steel70,000 kg × 0.49 × 155about 5.3 GJ
Dry part of the sheets48,000 kg × 0.9 × 155about 6.7 GJ
Water in the sheets12,000 kg × 4.19 × 155about 7.8 GJ
Total for heat-upabout 19.8 GJ

Steam: 19,800,000 kJ ÷ 2030 kJ/kg ≈ 9,800 kg. Average consumption over the 3.5 hours of heat-up ≈ 2.8 t/h.

What the example shows:

  • In this example the water in the sheet and the sheet itself take more heat than the steel. The wetter the load, the more steam: water has a heat capacity four to five times higher than the dry sheet.
  • The heat-up time divides the consumption directly. Spirax Sarco says that if 10 minutes can be allowed for heat-up instead of 5, the initial steam consumption is halved. Stretching the heat-up is the cheapest way to reduce the peak. But the heat-up regime is part of the technology, and it can be changed only together with the technologist.
  • This is only the heat-up. On top of it come heat losses through the walls, the lid and the steam line. Losses grow with temperature. In the Spirax Sarco example an uninsulated steam pipe would lose about 14 times more heat than an insulated one, so the insulation of the autoclave and the steam line is checked before the boiler is calculated.
  • This is an average consumption. The instantaneous consumption differs in different minutes of the heat-up. It will be shown by a flowmeter on a working autoclave or by the manufacturing plant's calculation.

From consumers to the boiler

  1. Add up the consumers that work at the same time. Draw the day hour by hour: when each autoclave heats up, when it holds, when it releases pressure; when the steam curing chambers are loaded. Add up the consumptions in the heaviest hour.
  2. Compare the peak with the average. Spirax Sarco writes that peak loads are especially hard in industries with batch cycles; among its examples are the production of lightweight concrete blocks and rubber production with large autoclaves. Spacing out the starts of processes in time is called by Spirax Sarco an organisational way to smooth the peak, but short peaks cannot be removed this way. A boiler chosen for the peak is too large for the average load and runs at low efficiency. The overlap of the heat-ups of several autoclaves is reduced by spacing out the cycles, and a short peak can be taken by a steam accumulator: it gives up steam when demand is above what the boiler gives at that minute.
  3. Convert the catalogue figure to the actual one. The "from and at 100 °C" rating means the steam output as if the feedwater arrived at 100 °C and the steam were produced at atmospheric pressure; for each kilogram of steam the boiler gives 2257 kJ. Cold feedwater and a high working pressure reduce the actual output at the same fuel consumption.

How to recalculate: actual output ≈ "from and at" rating × 2257 ÷ (steam enthalpy − feedwater enthalpy). By the NIST tables for an absolute pressure of about 1.0 MPa the enthalpy of saturated steam is about 2777 kJ/kg, of water at 50 °C about 209 kJ/kg, at 20 °C about 84 kJ/kg. The factor comes out about 0.88 with feedwater at 50 °C and about 0.84 at 20 °C. A boiler of "4 t/h from and at" on cold water will give about 3.4 t/h. That is why the return of hot condensate to the boiler noticeably affects whether the boiler will be enough.

For orientation: 1 t/h of steam "from and at 100 °C" is about 627 kW of heat (1000 kg × 2257 kJ/kg ÷ 3600 s).

What to send the plant to select a boiler

  • A list of steam consumers: autoclaves (volume, working pressure, mass of shell and cars), steam curing chambers (volume, temperature), others.
  • Regimes: time of heat-up, hold and release, number of cycles per day, schedule by hours.
  • The mass of the load and the moisture of the sheet from your own measurement.
  • The length of the steam line and whether it is insulated.
  • The feedwater temperature: whether there is condensate return, whether there is a deaerator.
  • The fuel and the water analysis; these are covered in detail in the articles on choosing a boiler and on water for the boiler.

Ask the plant to state the steam output at your working pressure and your feedwater temperature, and not only "from and at". In Uzbekistan the technical regulation on the safety of equipment under excess pressure (Cabinet Resolution No. 493 of 04.08.2025, clause 138) requires the passport of a boiler to state the nominal, the lowest and the highest permissible steam output in t/h; the nominal water temperature at the boiler inlet is stated there too. Check these three figures against your own calculation of the peak and of the minimum load at night.

Safety

The boiler, the autoclave and the steam line are equipment under pressure. Boilers with a capacity of more than 0.002 m³ for steam at a pressure above 0.05 MPa fall under the technical regulation on the safety of equipment under excess pressure. A boiler that "does not keep up" is not pushed above its passport output and the pressure is not raised above what is permitted. If the boiler is not enough, they change the schedule of cycles, install an accumulator or a second boiler by design. Which permits are needed before start-up is covered in the article on permits for the boiler.

How we do it

  • We select the boiler at the manufacturing plant for your consumers, pressure and fuel. We pass your calculation and the source data to the plant and ask it for its calculation of steam output under your conditions. What we find, with the plant's specifications, we send before the order.
  • Supply is under a contract with the manufacturing plant. We inspect the lot at the plant before shipment: completeness, marking, passport, packaging, with a report and photos.
  • Defects confirmed by a report are replaced by the manufacturing plant under the contract with us; we handle the replacement.
  • We handle the import formalities.

What this article relies on

Below are the documents and materials we refer to, so that you can check what is said for yourself.

Standards and documents

  • Resolution of the Cabinet of Ministers of the Republic of Uzbekistan No. 493 of 04.08.2025 "On approval of the Technical Regulation on the safety of equipment operating under excess pressure": clause 2 "d" (scope: boilers with a capacity of more than 0.002 m³ for steam at a pressure of more than 0.05 MPa), clause 138 "b" (nominal, lowest and highest permissible steam output in the boiler passport, t/h; nominal water temperature at the boiler inlet). Text in the state language; checked 30.10.2026text ↗
  • EN 1992-1-2:2004 "Eurocode 2. Design of concrete structures. Part 1-2: Structural fire design", clause 3.3.2: specific heat of dry concrete 900 J/(kg·K) at 20–100 °C, growing above 100 °C. The 2004 edition; a new edition of the standard came out in 2023. The text of the standard is distributed by CEN and the national standards bodies

Reference materials

  • Rybyev I. A. "Building Materials Science" (Строительное материаловедение), section "Fundamentals of asbestos-cement product manufacturing": steam curing chambers 50–60 °C, humidity 90–95 %, 10–14 h, warehouse 5–7 days; autoclave at a steam pressure of 0.8 MPastudme.org ↗
  • Patent US 7972433 B2 "Fiber reinforced cement composition and products and manufacturing process": pre-curing 40–80 °C 12–24 h, autoclave 150–180 °C, rise 3.5 h, hold 6.5 h, decrease 6 hpatents.google.com ↗
  • Spirax Sarco, "Steam consumption of pipes and air heaters": what steam consumption for heat-up depends on, heat capacity of steel 0.49 kJ/(kg·°C), heat-up against running load, effect of heat-up time and insulationspiraxsarco.com ↗
  • Spirax Sarco, "Methods of estimating steam consumption": heat-up and heat losses, measuring consumption with a flowmeterspiraxsarco.com ↗
  • Spirax Sarco, "Boiler ratings": what "from and at 100 °C" means, 2257 kJ/kg, effect of pressure and feedwater temperaturespiraxsarco.com ↗
  • Spirax Sarco, "Steam accumulators": peak loads of batch industries (including lightweight concrete blocks and large autoclaves of rubber production), a boiler sized for the peak and low efficiency, spacing out of starts, the accumulatorspiraxsarco.com ↗
  • NIST Chemistry WebBook, "Saturation properties for water": saturation temperature, enthalpy of water and steamwebbook.nist.gov ↗

The calculation in the article is an estimate for a conversation with the plant. The final steam output is calculated by the designer or the boiler manufacturing plant from your data.

Related catalog items

  • 001Steam boiler for a fiber-cement line

    Steam boiler for a fiber-cement line

    TMN-XHB-08Xinhuibo

  • 002Autoclave for fiber-cement sheet

    Autoclave for fiber-cement sheet

    TMN-XHB-03Xinhuibo

  • 003

    DZL packaged steam boiler, coal and biomass

    TMN-STG-01Sitong

  • 004

    SZL assembled steam boiler, coal and biomass

    TMN-STG-02Sitong

Selection for your machine

Need an autoclave or boiler?

We will calculate the steam for your consumers and select a boiler from the manufacturing plant.

Request

Ask about your machine

A part number is enough. A drawing or a photo of the unit speeds up sourcing but is not required.

Up to 3 files: photos (JPG, PNG, WEBP, HEIC) or PDF, up to 15 MB in total

By sending the request you consent to the processing of the data provided for the purpose of replying to it, as described in the Privacy Policy.