Verifying scales and instruments at a slate plant: law and GOST

A sheet test result is worth as much as the instrument it was obtained with. GOST 30340-2012 sets the accuracy of the scales, the caliper and the bending testing machine. The Uzbek law "On Metrology" names the areas where measurements are under state control: accounting of material assets, industrial safety, quality of certified products, conformity assessment. Instruments for such measurements are, as a general rule, verified; where the law allows calibration instead of verification, check with the metrology service.

Updated 9 min read

In short

9minutes to read

8sections

5sources

3catalog items

In this article

  1. 01What the owner and the chief mechanic need to decide
  2. 02What GOST 30340-2012 requires of instruments
  3. 03What the law of Uzbekistan says
  4. 04How verification works
  5. 05What changes from 1 January 2027
TableWhat GOST 30340-2012 requires of instruments5 rows →
Contents
  1. What the owner and the chief mechanic need to decide
  2. What GOST 30340-2012 requires of instruments
  3. What the law of Uzbekistan says
  4. How verification works
  5. What changes from 1 January 2027
  6. How to put things in order: steps
  7. Safety
  8. How we do it

A sheet test report is a figure from an instrument. If the scales are off by a gram and the bending testing machine by tens of newtons, the report proves nothing: not to the buyer, not to the certification body, not to you yourselves when you look into a claim. So the instruments of the plant laboratory and the shop have two requirements. The first is technical: the sheet standard sets how accurate the instrument must be. The second is legal: the law on metrology defines in which areas measurements are under state control and the instrument must be verified. Below is what exactly GOST 30340-2012 requires, what the law of Uzbekistan says and how to put the plant's instruments in order. The legal part was checked against the texts on lex.uz on 30.10.2026.

What the owner and the chief mechanic need to decide

  • A list of instruments. Draw up a list of everything that measures at the plant: raw material receiving and shipping scales, batchers, laboratory scales, the bending testing machine, the pendulum impact tester, the drying oven, thermometers, measuring tools, the pressure gauges of the boiler and the autoclave.
  • What each instrument is for. For each one state where its result goes: into accounting and settlements with the supplier, into a report for the buyer or for certification, into the safety of equipment under pressure, or only into internal adjustment.
  • Verification or calibration. Whether verification is needed or calibration is enough depends on the answer to the previous question.
  • A schedule. Each instrument has a date of the next verification or calibration. An instrument whose term has expired must not give figures for a report.

What GOST 30340-2012 requires of instruments

GOST 30340-2012 "Chrysotile-cement corrugated sheets" is an interstate standard; the date of introduction in its text is 1 July 2013. Uzbekistan voted for its adoption. In the section on control methods the standard sets the measuring instruments and their accuracy.

TestWhat the standard requires
Dimensions and shape (8.3.1)tape measure with a scale division of not more than 1 mm, caliper, depth caliper, thickness gauge, ruler, square. Error not more than ±0.1 mm when measuring thickness and not more than ±1.0 mm for other dimensions. A non-standard tool is allowed if it has passed metrological certification
Bending strength (8.4.1)a device that loads no faster than 50 N/s when testing specimens and 300 N/s when testing products and measures the breaking load with an error of not more than 5 N
Load through a bar (8.5.1)a device that loads no faster than 200 N/s and measures the load with an error of not more than ±1 %
Density (8.8.1)a drying oven holding 105–110 °C, laboratory scales with an error of not more than ±0.08 g, a thermometer
Frost resistance (8.10.1)a freezer giving an air temperature of not higher than minus 15 °C

If the laboratory's instrument cannot confirm this accuracy with a document, the test result can be disputed. The document on accuracy is a verification certificate or a calibration certificate.

What the law of Uzbekistan says

The Law "On Metrology" is in force in its new version adopted by Law No. ZRU-614 of 07.04.2020; the latest amendments were made in 2023 and have applied since 28.01.2024.

Verification and calibration are not the same thing. Under Article 3 of the law, verification confirms that the instrument meets the established metrological requirements. Calibration establishes its metrological characteristics. Put simply: verification answers "fit or not" against the mandatory requirements, calibration says "how far off it is".

Where measurements are under state control. Article 20 lists 15 areas. For a slate plant these matter:

  • accounting of material assets and fuel and energy resources (2nd in the list): the scales on which cement and fibre are received and sheet is shipped, gas and electricity meters (their periodic verification follows separate administrative regulations, clause 1 of the Verification Rules);
  • ensuring industrial safety (7th): measurements on equipment under pressure;
  • occupational safety (9th);
  • safety and quality of certified products (10th);
  • conformity assessment of products (15th): tests for a certificate or a declaration.

Who verifies. Under Article 25, verification is carried out by the accredited Uzbek National Institute of Metrology and the metrology services of republican bodies and of economic management bodies. Instruments that are not in the list of groups of state significance can also be verified by the metrology services of legal entities. The lists of groups of instruments subject to verification are approved by the authorised state body.

Calibration. Under Article 26 it is carried out by accredited metrology services. Instruments that are used outside the areas named in paragraphs two to ten of part one of Article 20 can be calibrated. These are the first nine areas of the list, from health care to occupational safety, including accounting and industrial safety. The results of calibration by an accredited service can be used in verification.

For certified products and conformity assessment (areas 10 and 15) the law does not forbid calibration, but the Verification Rules (clause 3) put these areas under verification. What document is needed for an instrument used for tests for a certificate, find out from the certification body and the metrology service before the tests.

Liability. Article 32: those guilty of violating the legislation on metrology bear liability in the established order.

How verification works

The procedure is set by the Verification Rules, Appendix No. 3 to Cabinet of Ministers Resolution No. 528 of 29.08.2020.

  • What is verified. Instruments entered in the State Register of Measuring Instruments and used in the areas of state control (clauses 2–3). Others can be verified voluntarily (clause 6). Teaching instruments and indicators that only show a change of a quantity without assessing its value are not subject to verification (clause 4).
  • Initial verification (clause 8). All units of instruments are subject to it, except those that have passed metrological certification.
  • Types of verification (clause 7). Initial: on release from production and after repair. Periodic: at the end of the verification interval. Extraordinary: if the seal is broken, the verification document is lost, during adjustment, on putting into operation after storage longer than one verification interval. There are also inspection verification (during supervision) and expert verification (in a dispute).
  • If the instrument is fit (clauses 26–27). A report is drawn up and a verification certificate is issued. The impression of the verification mark is put on the instrument, on the seal or in the operating documents.
  • If it is not fit (clauses 29–30). A notice of unfitness is issued, the mark is cancelled. After repair the instrument is verified again.
  • Verification on site (clause 24). If a large instrument is verified at the plant, the applicant ensures delivery of the verifier's reference instruments to the place of verification and back. This concerns, for example, large scales that cannot be taken away.

Calibration is regulated by the Calibration Rules, Appendix No. 5 to the same resolution. The frequency of calibration is set by the methods, and it must not exceed the verification interval for the same instrument (clause 5). A calibration certificate is issued on the result (clause 13).

What changes from 1 January 2027

By Order of the Agency for Technical Regulation No. 69 of 02.09.2026 (reg. No. 3606-1), the order "On approval of the List of categories of measuring instruments subject to verification" has been recognised as no longer in force. The new order enters into force on 01.01.2027. What will replace the list is not stated in its card on lex.uz. So at the start of 2027, before planning the verifications for the year, check which list is in force and check your instruments against it.

The procedure is changing: before planning verifications and before tests for certification, check it with the metrology service or a lawyer. Kazakhstan, Kyrgyzstan and Tajikistan have their own laws on metrology; this article does not cover them.

How to put things in order: steps

  1. Inventory of instruments. Name, type, serial number, where it stands, what it measures, where the result goes.
  2. Marking by area. Against each instrument, the area from Article 20 or the note "internal adjustment".
  3. Check against the list. For instruments from the areas of control: whether their group is in the current list of instruments subject to verification and what its verification interval is.
  4. Documents. For each instrument a verification certificate or a calibration certificate. No document: the instrument gives no figure for a report until it is verified or calibrated.
  5. Schedule. Terms in one log, one person responsible. An instrument after repair and after long storage goes to verification first.
  6. A new instrument from China. When ordering, ask the manufacturing plant for a calibration document and a passport with the metrological characteristics. Under Article 24 of the law, instruments for the areas of Article 20 that are imported undergo state tests and type approval or metrological certification. What exactly will be needed for your instrument, find out from the metrology service before ordering.

Safety

Pressure gauges, safety valves and level sensors on the boiler and the autoclave protect people. An instrument with unclear verification on equipment under pressure is a reason to stop and check, not to keep working "out of habit". The procedure for testing and servicing this equipment is in the articles on the safety of the press and the autoclave and on permits for the boiler.

How we do it

  • Laboratory instruments, scales and instruments for the boiler and the autoclave we select at the manufacturing plant to the requirements of your standard: range, error, version. What we find, with the plant's specifications, we send before the order.
  • From the manufacturing plant we request a passport and a calibration document and hand them over with the delivery.
  • We inspect the lot at the plant before shipment: completeness, marking, passport, packaging, with a report and photos. Defects confirmed by a report are replaced by the manufacturing plant under the contract with us.

What this article relies on

Below are the documents and materials we refer to, so that you can check what is said for yourself.

Standards and documents

  • Law of the Republic of Uzbekistan "On Metrology" in the version of Law No. ZRU-614 of 07.04.2020, version of 28.01.2024: Art. 3 (verification, calibration), Art. 20 (areas of control), Art. 21, Art. 24 (type approval, import), Art. 25 (verification), Art. 26 (calibration), Art. 32 (liability)text ↗
  • Resolution of the Cabinet of Ministers of the Republic of Uzbekistan No. 528 of 29.08.2020 "On additional measures to improve the procedure for providing metrological services in the Republic of Uzbekistan": Appendix No. 3 "Rules for verification of measuring instruments" (clauses 1–4, 6, 7, 8, 24, 26–27, 29–30), Appendix No. 5 "Rules for calibration of measuring instruments" (clauses 5, 13)text ↗
  • Order of the Uzbek Agency for Technical Regulation No. 69 of 02.09.2026, reg. Ministry of Justice No. 3606-1 of 04.09.2026, "On recognising as no longer in force the order 'On approval of the List of categories of measuring instruments subject to verification'", enters into force on 01.01.2027; text of the act in the state languagetext ↗
  • GOST 30340-2012 "Chrysotile-cement corrugated sheets. Specifications": 8.3.1, 8.4.1, 8.5.1, 8.8.1, 8.10.1 (test equipment and its accuracy)text ↗

Reference materials

  • Search cards in the lex.uz database for "средств измерений подлежащих поверке" (measuring instruments subject to verification): current and cancelled lists of groups of measuring instrumentslex.uz ↗

Checked against the versions on lex.uz on 30.10.2026. The text of Resolution No. 528 on lex.uz in Russian is marked as an unofficial translation; in a dispute, check against the text in the state language.

Related catalog items

  • 001Fiber-cement and asbestos-cement sheet production line

    Fiber-cement and asbestos-cement sheet production line

    TMN-XHB-01Xinhuibo

  • 002Autoclave for fiber-cement sheet

    Autoclave for fiber-cement sheet

    TMN-XHB-03Xinhuibo

  • 003Steam boiler for a fiber-cement line

    Steam boiler for a fiber-cement line

    TMN-XHB-08Xinhuibo

For slate plants

Felts, meshes and units for your line

We select from manufacturing plants in China by nameplate photo and machine dimensions. Send a photo of the plate and we will tell you what can be ordered.

Request

Ask about your machine

A part number is enough. A drawing or a photo of the unit speeds up sourcing but is not required.

Up to 3 files: photos (JPG, PNG, WEBP, HEIC) or PDF, up to 15 MB in total

By sending the request you consent to the processing of the data provided for the purpose of replying to it, as described in the Privacy Policy.