Batchers and scales: why mix accuracy decides defects
A slate sheet depends on the ratio of cement, fibre and water. If the cement or fibre scales lie, the slurry composition changes from batch to batch, and it shows on the sheet: sometimes brittle, sometimes loose, sometimes of uneven thickness. So the scales are checked with test weights, the load cells and indicator are kept in order, and the flow of water and pulp is checked against the regulations.
In short
5minutes to read
7sections
5sources
4catalog items
In this article
- 01What the chief engineer and the buyer should decide
- 02What is batched by weight and what by volume
- 03How batcher scales are built
- 04Verification and calibration
- 05How a batcher error looks on the sheet
Contents
A slate sheet is cement, fibre, sometimes ground sand and additives, bound by water in a certain ratio. The recipe is set by the process regulations, and it is the batchers that keep to it. If the cement scales show more than there really is, less cement goes into the slurry, and the sheet comes out loose and weak. If the fibre scales lie, the reinforcement changes, and the sheet becomes brittle or forms badly. If the supply of water or pulp drifts, the concentration in the vats changes, and the sheet comes out of uneven thickness. So the accuracy of the batch is not bookkeeping but a direct cause of defects.
What the chief engineer and the buyer should decide
- The list of scales and batchers. Which are installed, the range, the accuracy class, and when each was last checked.
- Weights and the checking procedure. Whether the plant has test weights or a procedure for checking with a known load, and who checks and how often.
- Verification. Whether your scales need verification or calibration by a metrology body, under the rules of your country. This is clarified with the local metrology service.
- Stock. A load cell, a weighing indicator, a sensor cable: without them the batcher stands, and the whole line with it.
What is batched by weight and what by volume
| Component | How it is usually batched | Why |
|---|---|---|
| Cement | by weight, hopper scales or a weighing screw | the main component, strength depends on it |
| Dry fibre, sand, additives | by weight | the share is small, so an error is more noticeable |
| Cellulose as pulp | by volume at a known concentration | pulp is easier to measure by volume, but the concentration must be checked |
| Water and recirculated water | by volume or by flowmeter | there is a lot of it, and the concentration in the vats is evened out with water |
How exactly it is arranged on your line is shown by the slurry preparation diagram. What matters is to understand that everything batched by volume depends on concentration. If the pulp is thicker today than yesterday, the same volume carries more fibre.
How batcher scales are built
A hopper or bucket hangs on load cells. The cells give a weak signal, the weighing indicator turns it into a reading and passes it to the controller. The controller opens and closes a gate or switches on a screw until the set mass is reached.
What breaks and wears out:
- load cells: from impacts, overload, moisture in the cable, welding nearby without disconnecting;
- mechanics: the hopper rests against the frame, a pipe or caked cement, and part of the weight bypasses the cells;
- flexible connectors: hardened or stretched sleeves "hang" the hopper;
- indicator and analog input of the controller: calibration failure, interference, worn connectors;
- gate and screw: leakage after the "stop" command, and the excess goes into the batch.
Verification and calibration
The international recommendation OIML R 76 describes non-automatic weighing instruments and their accuracy classes: the class is set by the verification scale interval and the number of intervals. The smallest load, below which the error becomes too large, is also standardized. For batcher scales this means a simple thing: the dose must be far from the lower edge of the scale range.
The checking procedure in industry instructions is the same: the scales are loaded in steps with test weights or a known load across the whole working range, at each step the reading is compared with the actual mass, and it is seen whether the difference falls within the tolerance. If it does not, the indicator is calibrated and the mechanical cause is looked for.
What to check between calibrations:
- the zero of the empty hopper at the start of the shift;
- whether cement has caked on the walls and the gate;
- whether the hopper hangs freely and does not touch the frame;
- whether the cement consumption for the shift by the scales agrees with the cement received into the silo.
How a batcher error looks on the sheet
| What you see | What to check in batching |
|---|---|
| Weak sheet, crumbling edge, low bending strength | cement scales, gate leakage, caking in the hopper |
| Brittle sheet, breaks at demolding and stacking | the fibre dose, pulp concentration |
| Thickness wanders from batch to batch | the supply of water and pulp, concentration in the vats |
| Defects in jumps, not constantly | scale mechanics: contact, caking, a cell |
This is a hint, not a diagnosis: the same signs are also given by the felt, the vacuum and the curing. So when defects start, the first thing is to check the scale zero and compare consumption, which is quick.
What to attach to a request for scale parts
- A photo of the load cell nameplate: model, rated load, sensitivity.
- The cell mounting diagram and how many cells there are on the hopper.
- A photo and model of the weighing indicator, and its wiring diagram to the controller.
- The range of the scales and the required accuracy from the passport.
How we do it
- From the photo, dimensions and the passport of the unit, we look for the item at the manufacturing plant. What we find, with the price, photos and specifications, we send before the order.
- Where the answer has to come from the plant (the composition of the system, the program, commissioning), we ask the plant and pass on its word.
What this article relies on
Below are the documents and materials we refer to, so that you can check what is said for yourself.
Standards and documents
- OIML R 76 "Non-automatic weighing instruments", 2006 amendment: accuracy classes, verification scale interval, minimum capacitytext ↗
Reference materials
- MEKA, "Calibration in concrete batching plants: a step-by-step guide": calibration of batcher scales, references to EN 45501 and OIML R 76mekaglobal.com ↗
- WeighTech, "Concrete plants, ready mix": load cells of hopper scales and ways of mounting themweightechusa.com ↗
- Rybyev I. A. "Building Materials Science" (Строительное материаловедение), section "Fundamentals of asbestos-cement product manufacturing": the ratio of water to dry mix is set by calculation, the consistency in the vats is held by feeding recirculated waterstudme.org ↗
- taminota.com catalog: weighing indicator for platform and hopper scales, manufacturer's description.
The recipe and batching tolerances are set by the process regulations of your plant; the tolerance figures are deliberately not given here.