Starting a new line: what goes wrong in the first weeks
In the first weeks a new line almost always gives less sheet and more rejects than promised: the slurry and felts are not yet matched to your raw materials and water, the shifts are learning, the units are running in, small installation flaws surface one after another. This is normal if every stoppage and every kind of reject is recorded: these records are needed both for tuning and for the warranty.
In short
5minutes to read
5sections
4sources
4catalog items
In this article
The first sheet from a new line is not yet output. Between the first good sheet and stable operation at design output there is a ramp-up period, and at any production it goes with stoppages and rejects. The causes are usually the same: the slurry and felts are not matched to your raw materials, the water is not the water on which the line was started at the manufacturer, the shifts do not yet know how to work, and small installation flaws surface one after another. In this period the owner should aim not to "push output" but to make sure that every stoppage and every kind of reject is recorded and analysed together with the engineers of the manufacturing plant.
What usually goes wrong
Slurry for your raw materials
The manufacturing plant gives the slurry recipe from its experience and from samples. Your cement, fiber, sand and water behave differently. The slurry may hold worse on the screen, give up water more slowly or give a weak layer. The recipe and the order of dosing are tuned on site, from the results of laboratory checks of the sheet. If in the first weeks the sheet delaminates or comes out of uneven thickness, start with the slurry.
Felts and screens
The first felts are fitted on the manufacturer's recommendation. On your slurry they may clog faster or release water worse. Note how long each felt ran and why it was taken off: these records are the basis for choosing felts later. How to test a new felt is in a separate article.
Water
On the Hatschek machine, water goes into the slurry and to washing the felt and screens, and then returns to circulation. If sediment accumulates in the recirculated water or its composition changes, this affects the slurry and the felt. The recirculation system is checked and tuned in the very first weeks.
People
Operators, the technologist, the mechanic and the electrician learn on a running line. Until the shifts gain experience, there are more stoppages and changeovers from format to format take longer. Training during start-up is part of the contract; there is a separate article about it.
Units and installation
Running in of bearings and drives, retightening of fastenings, leaks in the press hydraulics, tuning of interlocks and sensors. Some flaws come from installation, some from manufacturing. They can be told apart only by the records.
The bottleneck
When the forming machine begins to keep up, it becomes visible which stage limits output: the press, the curing chambers, the autoclave, the demoulding or the slurry feed.
What to record
Start the log from the first day of start-up:
- Every stoppage: date, time, unit, what happened, what was done, how long it stood.
- Rejects: kind (delamination, cracks, uneven thickness, edge), quantity, shift, what was changed afterwards.
- Modes and recipe: what was changed and when, with reference to the result of laboratory checks.
- Consumables: which felt, screen, knife was fitted and how long it ran.
- Remarks to the manufacturer: what does not work under the contract or the TS, when it was reported, what was answered.
Every remark to the manufacturer is in writing, with photos and a date. If a unit fails in the warranty period, the question "defect of the unit or operating error" is decided from these records and from the installation protocols.
What the owner must do in this period
- Not release the manufacturer's engineers from the site until the line has passed acceptance under the contract.
- Not sign the acceptance act until the output and quality written into the contract are confirmed.
- Keep a stock of felts, screens, knives and seals: until the slurry and felts are matched, they may be used up faster than usual.
- Once a week, go through the log with the technologist, the mechanic and the manufacturer's engineers.
Engineering layer: for the technologist and the mechanic
- Technologist: first the stability of the slurry: concentration, uniformity, order of loading. Then the thickness and strength of the sheet. Do not change the curing modes at the same time as the slurry: otherwise you will not understand what worked. The modes for your line follow the process regulations; record every deviation.
- Mechanic: monitoring of heat and vibration of the bearings, felt tension and tracking, condition of the press seals. The initial measurements from the factory tests are the baseline for comparison.
- Electrician: protection trips, sensor faults and controller communication failures go into the log, with the text of the alarm message.
How we do it
- Supervised installation and start-up are done by the manufacturing plant; we organize the trip of its engineers, translation and access to the site. This leaves fewer grounds for a dispute of "defect of the unit or installation error".
- A defect noted in the act is replaced in the manner and within the time set in the supply contract. We are the ones who demand the replacement from the plant.
- From the photo, dimensions and passport of the unit, we look for the item at the manufacturing plant. What we find, with price, photos and specifications, we send before the order.
What this article relies on
Below are the documents and materials we refer to, so that you can check what is said for yourself.
Reference materials
- "Identification of problem types during production ramp-up" (HAL): ramp-up as the period from the first product to stable output, recurring types of problemshal.archives-ouvertes.fr ↗
- Chalmers University, "Problems encountered in a production ramp-up — a study from a managerial and organizational perspective": organizational causes of problems during ramp-upodr.chalmers.se ↗
- Uhlmann, "Ramp-up support": during start-up, short stoppages and faults occur most oftenuhlmann.de ↗
- Rybyev I. A. "Building Materials Science" (Строительное материаловедение), section "Fundamentals of asbestos-cement product manufacturing": dependence of quality on fiber grinding, dosing, slurry uniformity, condition of the felt; recirculated waterstudme.org ↗
The procedure for the first weeks is drawn up from general studies of production ramp-up and the design of the Hatschek machine; the modes and recipe for your line are given by the process regulations and the manufacturer's engineers.