The GOST for the chrysotile-cement sheet says one thing about cement: the sheet is made from chrysotile and Portland cement, and the raw material must meet its own standards. Which cement exactly to take is set by the plant's technological regulations. General-purpose cement is supplied to GOST 31108-2020, and the general rules of acceptance and storage are given by GOST 30515-2013. Below is what to read in the quality document, how to take samples and how to store the lot.

Updated 9 min read

In short

9minutes to read

7sections

5sources

1catalog item

In this article

  1. 01What the GOST for the sheet says
  2. 02What cement comes in supply
  3. 03What to read in the quality document
  4. 04What to check with your own resources
  5. 05Storage and periods
TableWhat cement comes in supply6 rows →
Contents
  1. What the GOST for the sheet says
  2. What cement comes in supply
  3. What to read in the quality document
  4. What to check with your own resources
  5. Storage and periods
  6. Safety of people
  7. How we do it

A chrysotile-cement sheet is made from chrysotile and Portland cement, but the standards for the sheet itself say little about cement. So the plant has to put the cement requirements together itself: from the technological regulations of the line, from the cement standard and from the contract with the supplier. Below is what the standards say and what of it to check on every lot.

What the GOST for the sheet says

GOST 30340-2012 "Chrysotile-cement corrugated sheets" applies to the corrugated sheet, and GOST 18124-2012 "Chrysotile-cement flat sheets" to the flat one. Both are interstate standards. Among others, Uzbekistan, Kazakhstan, Kyrgyzstan and Tajikistan voted for their adoption.

Both standards say three things about the raw material:

  • chrysotile and Portland cement are used in making the sheets;
  • the raw materials and materials must meet the current standards and technical specifications for them;
  • the specific effective activity of natural radionuclides in the raw material must not exceed the limits of GOST 30108.

The GOST for the sheet sets neither the type of cement, nor the strength class, nor the fineness of grinding. That is decided by the technological regulations of your line: they must record which cement is accepted, to which standard and with which indicators. If the regulations do not have this, start by writing it down.

What cement comes in supply

General-purpose cement in the countries that adopted the standard is supplied to GOST 31108-2020 "General construction cements". Armenia, Belarus, Kyrgyzstan, Russia and Uzbekistan voted for it. The standard divides cements into six types by composition:

TypeNameClinker in the composition, %
ЦЕМ 0Portland cement without additives100
ЦЕМ IPortland cement95–100
ЦЕМ IIPortland cement with mineral additivesless, by subtype
ЦЕМ IIIPortland blastfurnace slag cementless, by subtype
ЦЕМ IVpozzolanic cementless, by subtype
ЦЕМ Vcomposite cementless, by subtype

By compressive strength at 28 days, cements are divided into classes 32.5, 42.5 and 52.5. By early-age strength they are divided into subclasses: Н — normal-hardening, Б — rapid-hardening, М — slow-hardening. Hence the designation, for example "Портландцемент ЦЕМ I 42,5Б ГОСТ 31108-2020" or "Бездобавочный портландцемент ЦЕМ 0 52,5Н ГОСТ 31108-2020".

The start of setting under this standard is not earlier than 75 minutes for class 32.5, not earlier than 60 minutes for 42.5 and not earlier than 45 minutes for 52.5. Special and technological additives in total are not more than 1.0 % of the cement mass, organic ones not more than 0.2 %.

An important proviso: GOST 31108-2020 does not apply to cements with special requirements that are produced to their own normative documents. If the supplier offers a special cement "for asbestos-cement products" to technical specifications, ask for these specifications in full and check them against the regulations. They should not be allowed to replace the regulations.

What to read in the quality document

Under GOST 31108-2020, every lot or part of it shipped to one address goes with a quality document. When accepting a lot, check:

What is statedWhy look at it
The manufacturer, its address and trademarkIs it the plant you have the contract with
The conventional designation of the cement and the standardIs it the type, class and subclass that are in the regulations
The lot number and the shipping dateThe warranty period is counted from the shipping date
The kind and amount of mineral additivesHas the supplier moved from ЦЕМ I to a cement with additives
Special and technological additivesWhat exactly was added at grinding
Activity for the previous 3 months and the coefficient of variationHow steadily the plant holds the strength
Effectiveness group on steamingStated only if it is in the contract
Radionuclides by periodic testsThe limit for cement is 370 Bq/kg
Warranty period, daysUp to what date the plant answers for the indicators
Numbers of wagons or trucksDo they match what arrived

Under the general standard GOST 30515-2013, the quality document also states the signs of false set, if there are any, and the list of indicators can be supplemented with the customer's requirements. So what your line lacks, for example the setting times of the lot or the fineness of grinding, can be written into the contract and received in every document.

Steaming. If the sheets harden in steaming chambers, pay attention to the effectiveness group of the cement on steaming. GOST 31108-2020 does not always determine it, only when the contract provides for it. It is tested under a standard regime of at least 11 hours at (80 ± 5) °C. This is the regime for testing cement, not the regime of your chambers: your own regime is set by the regulations of the line.

What to check with your own resources

  1. Checking against the document. The designation, the lot number, the transport numbers.
  2. Samples. In its acceptance rules, GOST 31108-2020 refers to GOST 30515-2013 (Uzbekistan is not on the list of those who voted for GOST 30515-2013, so check its validity in your country in the index of standards). GOST 30515-2013 describes consumer control like this: three laboratory samples are prepared from the combined sample. The first is sent to an accredited third-party laboratory, the second stays with the consumer or the manufacturer, the third is kept by the manufacturer for at least three months. In case of a claim, the second and third samples go to the manufacturer and the consumer. Each sample must be sent to the laboratory within three working days, not counting the day of sampling.
  3. Methods. Strength, setting times and other physical and mechanical indicators of cement under GOST 31108-2020 are determined to GOST 30744.
  4. Strength at 28 days. The lot is accepted and supplied before the strength tests are finished. If a significant defect turns up afterwards, the manufacturer is obliged to lower the strength class or change the subclass and notify the consumer within three days. So keep a sample of each lot until the results arrive.
  5. Your own laboratory. Which indicators the plant checks itself on every lot and which it gives to an outside laboratory is decided by the technologist; this too is worth writing into the regulations.

Storage and periods

GOST 30515-2013 requires cement to be stored separately by types, classes and strength subclasses. Bulk, in silos or other closed containers; in bags, in dry premises. Different cements must not be mixed, contaminated or wetted. Each silo must carry a visible inscription: the number, kind, type, class and subclass of the cement. If different cements have to be stored in turn in one silo, a new one is loaded only after the silo has been completely emptied. Bags are laid tightly on pallets in a stack not higher than 1.8 m or in two tiers with a total height of not more than 2.5 m.

The manufacturer guarantees that the cement conforms to the standard, provided the rules of transport and storage are observed, for 60 days from the shipping date, for rapid-hardening cements 45 days. The standard for a specific cement may extend this period. For a lot that has lain longer, the manufacturer's guarantee under the standard no longer applies; whether to put it into the slurry without retesting is decided by the technologist.

Safety of people

Cement is dangerous even before it gets into the slurry. The safety data sheet of one of the European manufacturers describes it like this:

  • on contact with water, cement gives a strongly alkaline solution, pH from 11 to 13.5; it irritates the skin and eyes, causes dermatitis and can seriously damage the skin;
  • dry or wet cement in the eyes can cause serious and irreversible damage. Do not rub the eye, immediately rinse the open eye with running water for at least 20 minutes and in any case see a doctor;
  • the dust irritates the respiratory tract;
  • a reducing agent for hexavalent chromium has been added to this manufacturer's cement. In wet storage or after the stated period, it may stop working early, and the cement may cause skin allergy. The period is stated in the waybill or on the bag. Whether there is a reducing agent in your cement, look in the supplier's safety data sheet;
  • the gloves must be waterproof, resistant to abrasion and to alkali.

Ask the supplier for the safety data sheet of your cement together with the first contract. It may differ from the one given.

Next to cement, the plant works with chrysotile, and the requirements there are stricter: they are covered in the article on chrysotile. For cutting and sawing finished sheets, GOST 30340-2012 assigns chrysotile-cement dust to hazard class IV and limits its concentration in the air of the working zone to 6 mg/m³. Which norms and means of protection are mandatory in the bag-opening and dosing areas of your plant is determined by the occupational safety rules of your country.

How we do it

  • We do not supply cement or chrysotile. We supply sheet production lines and spare parts for them.
  • We order equipment from the manufacturing plant under a contract and inspect the lot at the plant before shipment: dimensions, material, marking, packaging, with a report and photos.
  • A defect confirmed by a report is replaced by the manufacturing plant under the contract; we see the replacement through to you.

What this article relies on

Below are the documents and materials we refer to, so that you can check what is said for yourself.

Standards and documents

  • GOST 30340-2012 "Chrysotile-cement corrugated sheets. Specifications": clauses 5.2.1, 5.2.2, 5.2.4 (raw materials), clause 6.3 (dust), the list of voting countriestext ↗
  • GOST 18124-2012 "Chrysotile-cement flat sheets. Specifications": clauses 5.2.1, 5.2.2, the list of voting countriestext ↗
  • GOST 31108-2020 "General construction cements. Specifications": sections 1, 5, 7, clauses 6.2.2, 6.2.3, tables 1 and 2, clauses 10.1, 11.1, 11.5, 12.2, annex A, the list of voting countriestext ↗
  • GOST 30515-2013 "Cements. General specifications": clauses 7.4.8, 7.4.9, 8.2.5, 8.2.6, 10.2, section 12, the list of voting countriestext ↗

Reference materials

  • Heidelberg Materials, safety data sheet "Cement, Hydraulic Road Binder, Hydraulic Lime, Masonry Cement", version 3.2 of 11.09.2023: sections 2, 4, 8, 9heidelbergmaterials.de ↗

The texts of the standards were opened on 30.10.2026. Check the validity of a standard in your country in the national index of standards: the adoption of an interstate standard and its entry into force in a specific country are different steps.

Related catalog items

  • 001Fiber-cement and asbestos-cement sheet production line

    Fiber-cement and asbestos-cement sheet production line

    TMN-XHB-01Xinhuibo

For slate plants

Felts, meshes and units for your line

We select from manufacturing plants in China by nameplate photo and machine dimensions. Send a photo of the plate and we will tell you what can be ordered.

Request

Ask about your machine

A part number is enough. A drawing or a photo of the unit speeds up sourcing but is not required.

Up to 3 files: photos (JPG, PNG, WEBP, HEIC) or PDF, up to 15 MB in total

By sending the request you consent to the processing of the data provided for the purpose of replying to it, as described in the Privacy Policy.