When to order spare parts so you do not stand in the season
Count from the date the part must be in your hands: the start of the repair shutdown or the start of the sales season. From it subtract the production time, transport, customs and a reserve for the unexpected — that gives the last order day for each item. Felts, screens, parts to drawing and large bearings are ordered first; off-the-shelf consumables last.
In short
4minutes to read
6sections
4sources
3catalog items
In this article
- 01Why this matters for a slate plant in particular
- 02How to calculate the last order day
- 03Long and quick items
- 04Check before the shutdown
- 05Typical mistakes
Contents
The order is planned from the date the part must be in your hands: the start of the repair shutdown or the start of the season when the line must run without breaks. From that date subtract the production time, the transport, the border formalities and a reserve for the unexpected. The result is the last order day, separately for each item. First you order what is made to your size and brought from far away: felts, screens, parts to drawing, large bearings, knives. Last, what local suppliers have. How many days each step takes you ask the supplier for each item: there is no general figure here, and there cannot be.
Why this matters for a slate plant in particular
At many roofing sheet plants sales are uneven through the year. When demand is high the line is not stopped, and repair is moved to the time when sales are lower. So the plant has two key windows: a short repair shutdown, for which all the parts are needed at once, and the season, for which a stock of consumables is needed. Check this against your shipments by month for past years: that way you will see your own windows, not someone else's.
A felt is the most frequent consumable of the forming machine. It clogs with slurry, it is washed, and when washing no longer helps or the tensioner has reached its end, it is changed. If the felt runs out in the season, the machine will stop. How many felts you use per season is shown by the replacement log.
How to calculate the last order day
The method is simple, and it is used in preparing planned shutdowns at large plants: from the shutdown date you go backward through the suppliers' lead times.
- Readiness date. Set the day by which the part must be with you. For a repair, a few days before the shutdown, to have time to check it. For the season, before it starts.
- Time at the supplier. Ask how long the manufacturer takes to make this item. A felt to size and a part to drawing are made after the order, not taken from a shelf.
- Transport and formalities. Time on the road and at the border depends on the route and the load. What affects it is covered in the article on how cargo travels from China.
- Approval. Sourcing, your "yes", the contract, payment — these are also days, and they are often forgotten.
- Reserve. Add a reserve for delay. The more important the item, the bigger the reserve.
The readiness date minus the sum of the steps is the last order day. Write it in a table next to the item.
Long and quick items
| Group | Examples | When to order |
|---|---|---|
| Long, to your size | felts, screens, knives to drawing, shafts, templates, roll covers | first, by the last order day |
| Standard but rare | large bearings, gearboxes, motors of non-standard versions, pumps | together with the long ones or right after |
| Fast-moving | belts, small bearings, seals, filters, fasteners | closer to the shutdown, from local suppliers |
It is more sensible to gather the long and standard items into one order than to send ten small ones. How to draw up an annual request of a slate plant is covered in a separate article.
Check before the shutdown
Before the repair, compare what has arrived with what the work plan needs. It is convenient to do this twice: in advance, when a lagging order can still be sped up, and a few days before the shutdown. Unpack the arrived felts and parts and check them against the order: size, part number, quantity. A mistake is easier to correct before the shutdown than during it.
Typical mistakes
- Ordering after a breakdown. A part that is made to order does not make it to the season after a breakdown. Long items are ordered by plan, not after a failure.
- No replacement log. Without a record of when and what was changed, the number of felts and parts for the season is taken from memory.
- The last felt on the machine. If there is no spare felt and the new one is still on the way, any damage to the fabric stops the line.
- Everything in the last month. If all orders fall in the one month before the season, any delay at one supplier shifts the whole repair.
How we do it
- Items for the repair and the season we look for at the manufacturing plant by number, drawing or photo of the unit. What we find, with the price, photos and specifications, we send before the order.
- What affects transit time we tell you before the order.
- We inspect the lot at the plant before shipment: part number, dimensions, lot, packaging.
What this article relies on
Below are the documents and materials we refer to, so that you can check what is said for yourself.
Reference materials
- Oxmaint, "Long-lead parts planning for power plant maintenance": back-calculating order dates from the shutdown date, ranking by criticality, checking readiness before the shutdownoxmaint.com ↗
- iFactory, "Annual maintenance shutdown: textile mill overhaul planning": long items are ordered by the supplier's lead time, not a month before the shutdown; checking the work plan against stockifactoryapp.com ↗
- Patent application US 2007/0155272, background section: clogging of the felt with slurry on a fibre-cement machine, frequent washing, taking the felt off when the tensioner reaches its limitpatents.google.com ↗
- ISO 14224:2016, description on the Swedish Institute for Standards (SIS) site: collection of equipment failure and maintenance datasis.se ↗
Production and delivery times are deliberately not given in the article: they depend on the item, the plant and the route, and are asked of the supplier for each line.